Welcome to E H Humphries

Toby Carvery Bromsgrove

E H Humphries (Norton) Ltd was appointed to deliver the mechanical and electrical installation packages as part of the refurbishment and conversion of an existing Brewers Fayre public house into a new Toby Carvery restaurant for Mitchells & Butlers.

The wider project involved extensive internal and external refurbishment, including alterations to existing building services, kitchen and back-of-house modifications, customer area improvements, toilet refurbishment, external enhancements and associated specialist installations.

Working alongside multiple subcontractors and specialist trades, E H Humphries successfully delivered the mechanical and electrical works within an eight-week programme, supporting the transformation of the existing premises into a modern restaurant environment.

Mechanical Installation

The mechanical package involved significant upgrades to the building’s heating, water, drainage, gas and air conditioning systems.

Works included the installation of new boilers serving the restaurant and staff accommodation, with separate heating circuits and independent controls to provide greater flexibility and control.

The customer toilet facilities were refurbished with new sanitaryware, including wash hand basins, toilets and accessible toilet facilities, alongside new above-ground drainage and hot and cold water services.

A complete mechanical services installation was undertaken within the refurbished kitchen, including new water, waste and gas supplies to serve the replacement catering equipment. A new gas solenoid valve and control panel were installed to provide an upgraded gas safety control arrangement for the kitchen cook line.

Existing air conditioning systems were also addressed, with one obsolete unit replaced, four existing units serviced and recommissioned, and two new 10kW Samsung cassette units installed.

These improvements provided enhanced heating, cooling and building services infrastructure to support the restaurant’s operational requirements.

Electrical Installation

The electrical package focused on upgrading the lighting, power distribution and electrical infrastructure throughout the premises.

New LED lighting was installed internally and externally, complemented by a new dimming panel and lighting control system to provide flexible lighting levels and create different atmospheres throughout the restaurant.

External enhancements included festoon lighting, building illumination, LED rope lighting around the eaves and upgraded signage, improving the appearance of the premises.

Additional USB charging sockets were installed to enhance customer facilities, while new electrical supplies and distribution boards were provided to support the refurbished kitchen equipment.

The kitchen cook line supplies were installed through contactors, allowing the equipment to be shut down through the emergency stop system.

Further improvements included new electric panel heaters within the toilet facilities, each with individual thermostatic control, and upgraded back-of-house LED lighting incorporating PIR sensors to improve energy efficiency.

All electrical installation works were tested and inspected upon completion, with the appropriate certification provided in accordance with BS 7671.

Sustainability & Energy Efficiency

Energy efficiency was an important consideration within the refurbishment, with LED lighting installed throughout both internal and external areas.

The new lighting systems offer reduced energy consumption and lower heat output, while the dimming controls allow lighting levels to be adjusted to suit operational requirements.

Integrated PIR sensors within back-of-house areas help minimise unnecessary energy use, while the lighting control system can also help extend lamp life and reduce maintenance and replacement requirements.

The project was delivered in line with Mitchells & Butlers’ FY27 sustainability objectives, supporting a more energy-efficient and environmentally conscious restaurant environment.

Project Completion

Successfully delivered within an eight-week programme, the Toby Carvery Bromsgrove project demonstrates E H Humphries’ ability to deliver coordinated mechanical and electrical installations as part of a comprehensive hospitality refurbishment.

The completed works provide upgraded building services, improved customer facilities, modern kitchen infrastructure and energy-efficient lighting throughout the premises.

Through effective coordination and delivery across both mechanical and electrical disciplines, E H Humphries helped transform an existing Brewers Fayre into a new Toby Carvery restaurant, providing reliable and practical building services to support its ongoing operation.

Client:

Mitchells & Butlers

Duration:

6 Weeks

Location:

Worcestershire

Sector:

Hospitality

Testimonial