The CDC 2 Kidderminster was a fast tracked electrical project respectfully working in conjunction with various other trades whilst adhering to the project programme. All aspects of the electrical installation have been carried out to a high standard as to comply to BS7671: 2018 and as per the installation drawings provided by EXI.
Electrical:
- Thorlux smart scan lighting
- MK cable management systems
- Honeywell fire protection devices
- IPS units to provide protection to the treatment rooms
- Damper control circuits
- LV mechanical plant supplies
- LV distribution boards
- LV Sub- main to the roof plant room area
- Data installation
- Door access control
- Primary and secondary containment
- Nurse call system
- Bedhead trunking
Mechanical:
HEATING
Within ground floor plantroom 5, new dual pump set was installed, TPED 40-200. Pipework was then routed through the existing hospital risers to existing fourth floor plantroom. The pipework then splits to serve new AHU frost coil and 14 new duct mounted heater batteries within 4th floor roof void.
VENTILATION
- On the roof is located 1 new AHU
- New Actionair mode 6 smoke fire dampers
- The ductwork is heated via LPHW heater batteries controlled by BMS.
DOMESTIC WATER
- New tank cold water, hot water and hot water return pipework was routed through the ceiling void of CDC2.
- A new water service was routed from the existing R.O plant to the new R.O plantroom.
MEDICAL GAS
- New medical services where connected onto the existing services.
- New O2 and VAC
- New O2, Entonox, VAC, AGS,