This project covered the full electrical and mechanical installation for a newly built Community Centre in Southam. The centre was designed as a modern, energy-efficient facility for local residents, with multi-use spaces for events, meetings, and recreational activities.

Scope of Works

Electrical Installation

  • Main Panel and Meters – Installation of the main incoming panel and associated metering systems.
  • Sub-distribution – Distribution boards strategically placed throughout the building.
  • Small Power – General-purpose power outlets and dedicated circuits for equipment.
  • Lighting Systems – High-efficiency internal and external LED lighting.
  • Support Systems, Wiring & Controls – Complete containment, cabling, and intelligent control systems.
  • Power Supplies to Mechanical Systems – Dedicated circuits for all plantroom and mechanical equipment.
  • Telephone & Data – RJ45 points and structured CAT6 cabling for voice/data.
  • Fire Alarm System – Full addressable system with detectors, sounders, and call points.
  • Lightning Protection – Complete external lightning protection system to BS EN 62305 standards.
  • External Lighting – LED lighting for pathways, parking, and building perimeter.
  • Roof-mounted PVs – Supply and installation of photovoltaic solar panels for renewable energy generation.

Mechanical Installation

  • Installation of New Gas Main – New gas service and connection to plantroom.
  • New Plantroom Installation – Full mechanical plant installation including boilers, pumps, and associated controls.
  • Heating System – Wet heating system distributed throughout the building with radiators and controls.
  • Domestic Hot and Cold Water Systems – Pipework installation, water heaters, and sanitary fittings.
  • Drainage Systems – Above ground drainage including waste, soil, and vent systems.
  • Air Conditioning (AC) Systems – Installation of split systems for selected areas.
  • Ventilation Systems – Mechanical ventilation for WCs, kitchens, and common areas, ensuring proper airflow and compliance with building regulations.

Project Challenges

  • Completing a full M&E package within a tight 3-month window
  • Integration of renewables (PVs) and modern technologies in limited spatial zones
  • Coordinating closely with multiple trades during peak construction phases

Results

  • High-quality, on-time completion of all M&E systems
  • Fully tested, certified, and commissioned installations ready for occupancy
  • Delivered a future-proof, energy-efficient facility for the community
  • Strong collaboration resulted in zero major delays or rework

Key Takeaways

  • Successful delivery of a complete M&E scope within a fast-tracked programme
  • Strong site coordination and early-stage planning were key to meeting deadlines
  • Integration of renewable energy (PVs) aligns with sustainable building goals

Interclass PLC

Duration:

2 months

Value:

Mechanical: £196,400.00, Electrical: £119,674.00

Location:

Southam, Warwickshire

Sector:

Leisure